Mia Mia
← All projects

Dual occupancy · Completed

Dulwich Hill

Two new contemporary homes on a single suburban block, replacing a 1960s brick house. Curved timber-look battens, pale face brick and generous glazing give each home a distinctive street presence.

Project type
Dual occupancy (new build)
Location
Dulwich Hill, NSW
Our role
Design & construction
Completed
Early 2025
Completed home with curved timber-look battens and face brick, Dulwich Hill

Project timeline

All 7 stages complete · Completed and handed over

  1. Existing site
  2. Demolition
  3. Slab
  4. Structure
  5. Facade & roof
  6. Fitout
  7. Completion
  1. Nov 2023 – Apr 2024

    Stage 1 · Complete

    The existing site

    Site survey, title review and condition inspection of the original single-storey brick house and its deep rear garden.

    Original brick house and side drivewayDeep rear garden before worksRear carport and garden
  2. May 2024

    Stage 2 · Complete

    Demolition & site preparation

    Hazardous materials removal, demolition of the existing house and clearing the site ready for the new slab.

    Cleared site after demolitionExcavator and truck removing demolition materialSite preparation underway
  3. May – Jun 2024

    Stage 3 · Complete

    Slab & ground works

    Plumbing rough-in, vapour barrier, reinforcement and waffle-pod slab poured for both dwellings.

    Vapour barrier and plumbing set-outWaffle pods and reinforcement ready for the pourFreshly poured slab
  4. Jun – Jul 2024

    Stage 4 · Complete

    Brickwork & structure

    Ground-floor face brickwork and first-floor suspended slab, taking both homes up to their second level.

    Ground-floor brickwork risingFace brick walls and openingsFirst-floor slab formwork
  5. Aug – Sep 2024

    Stage 5 · Complete

    Upper level, roof & facade

    Upper-level walls, roofing, windows and the signature curved batten cladding, completed under full scaffold.

    Both homes under scaffoldFront elevation with the scaffold removedCurved batten cladding and face brick
  6. Sep – Oct 2024

    Stage 6 · Complete

    Interior fitout

    Linings, timber stairs, kitchens and custom joinery, with integrated lighting and a feature ceiling in the living areas.

    Timber staircase and skylightOpen-plan kitchen and livingCustom joinery with brass handles
  7. Oct 2024 – early 2025

    Stage 7 · Complete

    Finishes, completion & OC

    Final finishes, inspections and the Occupation Certificate, with both homes handed over ready to live in.

    Open-plan kitchen with curved islandAlfresco kitchen opening to the rear gardenMain bathroom with double vanity and brass tapware

Thinking about a dual occupancy on your block?

Start with a free consultation to talk through your site, budget and timeline.

Book a consultation View all projects